REPLACE POWER DISTRIBUTION PLINTH

Our Brief:

To replace a power distribution plinth that had become unsafe. The Body Corporate required minimal disruption to the individual owners. There was a need for completion on time and within the budgeted amount.

The Solution:

Communicating with the BC committee chairperson and all affected owners. Arranging a time outside of normal business hours that would cause minimal disruption to the owners.

Planning the time frame and job sequence to the nearest hour and contingency arrangements if existing equipment failed testing before re livening .

Carrying out the replacement of the plinth housing and pouring a new concrete base, reconnecting, testing and re livening; – all within 8 hours.

The job was completed within the expected time frame and on budget.